Premium Planner after Project Online: what to check before migrating

What is Planner Premium, for whom does it make sense and what checks to do on budgeting, reporting and EVM before migrating. And when to evaluate Project Operations, Excel or project control tools like ControlRoom.

Update, November 4, 2026. According to Microsoft's official lifecycle calendar, Project Online's retirement was set for September 30, 2026: the question is no longer "when to migrate" but "where to rebuild control". The five checks below remain the way to decide.

To those who pass the baton after Project Online

Project Online's retirement was set for September 30, 2026, and sales to new customers closed on October 1, 2025. For many Italian PMOs the question is on the table: migrate to Planner Premium, the path Microsoft has indicated for the transition, or look elsewhere? The answer doesn't lie in the name of the product: it lies in five concrete checks.

What is Planner Premium, with the facts

The new Microsoft Planner is a unified work management experience: it combines the simplicity of To Do, the collaboration of Planner, the power of Project and the intelligence of Copilot, as described in documentation for administrators. Two levels coexist within this experience: the basic plans, included in the standard Microsoft 365 licenses and with four views (Grid, Board, Planning, Charts), and the premium plans, which are the evolution of Project for the web.

To create premium plans you need the Planner Plan 1 license. Advanced features are unlocked with Planner & Project Plan 3 or Plan 5 and include, according to Microsoft documentation: report creation, timeline view (Gantt), task dependencies, sprints, custom fields, team workload and goal management. The Microsoft support page adds details: dependencies of all four types (FS, SS, SF, FF), critical path, milestones, custom calendars, People view, Assignments view, up to ten custom fields, and conditional coloring. For those coming from Project Online, the point of attention is precisely this: the distance between what Project Online did and what the premium plan documents.

For those who make sense Planner Premium

Planner Premium makes sense for those who plan with not too complex Gantts, work in distributed teams within Microsoft Teams, use sprints and boards and don't need a sophisticated costing engine. It's the natural choice for those who were already on Project for the web and for those who want to stay in the Microsoft 365 ecosystem with minimal friction. In both cases, the choice is decided on the numbers, not on the brochures. For a PMO that governs a portfolio with costs, contractual baselines and EVM, however, verification is mandatory: this is where Planner Premium must be put to the test before any migration promise.

The five checks before migrating

CheckConcrete questionWhat Microsoft sources say
BudgetingDo I manage costs, budgets and variances like in Project Online?Costing does not appear in the official list of premium features: it must be tested with a trial before deciding
ReportingDo my reports come out with the same detail?Reporting is an advanced feature, linked to Plan 3/5 licenses
EVMCalculating BCWS, BCWP and ACWP?The EVM is not listed among the features: it must be rebuilt or placed alongside something else
LicensesHow much do licenses cost for my team?Planner Plan 1 to create premium plans; Plan 3/5 for advanced features
Existing dataWhat migrates from Project Online and what doesn't?The data had to be exported before the retirement (September 30, 2026): check what is recreated and what is lost

The most important check is the first. In my opinion, a PMO that today lives on budgets and cost variances should not migrate to Planner Premium without first having recreated, on a test project, the complete cycle: baseline, costs, variance, reports. If the cycle doesn't return, it's not the instrument's fault: it's that you're looking for a function that isn't its job.

When to consider other options

  • Project Operations (Dynamics 365). It is the Microsoft solution for project-based companies: the official documentation he describes it as the application that connects sales, resourcing, project management and finance. It makes sense when the project is the business: orders, invoicing, margins.
  • Excel. For small teams and simple plans, the fastest and least expensive tool remains: the free tools for the progress report they start from there.
  • ControlRoom Free is an option to evaluate for individual control of plans, tasks, budget and costs, with AI reviews and exports within quota. It does not currently meet requirements for EVM, EAC, Project Online imports or multi-user collaboration. Future plans must not be evaluated as purchasable features.

Frequently asked questions

Does Planner Premium replace Project Online one-to-one?

No. It is the path that Microsoft has indicated for the transition, but it is not a clone of Project Online: some functions need to be checked, in particular budgeting and EVM. The test table above is designed exactly for this.

What license is needed for premium plans?

Planner Plan 1 to create premium plans and access additional views such as Timeline, People and Goals. Advanced features (reports, dependencies, sprints, custom fields, team load) require Planner & Project Plan 3 or Plan 5.

Is EVM available in Planner Premium?

It is not listed among the features documented by Microsoft. If the EVM is a requirement, it must be rebuilt with dedicated tools or supported with external calculations: the EVM guide explains what it takes to do this.

Do I have to decide right away?

The platform's deadline was September 30, 2026, and the export had to be done before it, while the service was active. Today the decision on the tool no longer has the urgency of the deadline, but it does require knowing which data you actually hold in your archive: start from that and from the five checks above.

The next step

The choice between Planner Premium and the alternatives is not made at a table: it is made with a field test. If you are comparing options after Project Online, the ControlRoom comparison page explains honestly what the tool replaces and what it doesn't, and the free demo shows you the environment with example data.