A useful project budget answers a practical question in the weekly review: where will this work land, not only what has already been invoiced? The minimum structure that supports that answer is small: six columns, a few formulas and one shared file.
You can download the Excel project budget template and adapt it to your cost lines. The sections below show what each column is for, how the picture changes once commitments and forecast are visible, and how to take the same figures into a ControlRoom Free review.
The numbers in the worked example are illustrative. They describe a realistic project shape, not a real client, measured result or forecast from ControlRoom.
The six columns that make the budget useful
| Column | What it contains | Why it helps the review |
|---|---|---|
| Line | The cost item, by WBS or by category: engineering, components, laboratory, installation | Keeps the budget comparable and easy to total |
| Budget | The approved value of the line | The reference the team agreed to work to |
| Actuals | Costs already incurred and recorded: invoices received, hours booked | Shows what has already been spent |
| Commitments | Orders issued but not yet recorded as actuals: purchase orders, signed contracts | Shows what is already spoken for |
| Forecast | The current estimate of the final cost of the line | Shows where the line is likely to land |
| Variance | Forecast minus budget | Shows where a decision or a closer look is needed |
Most sheets already have the first three columns. The last three turn a record of the past into a budget the team can govern. The guide to commitments versus actual costs explains why those two views belong side by side.
Illustrative example: a test-bench delivery
Illustrative example, not a real project. Imagine a six-month delivery of an industrial test bench, with an approved budget of €120,000. The figures below are sample amounts in euros, prepared for a mid-project review. They are not historical results.
| Line | Budget | Actuals | Commitments | Forecast | Variance |
|---|---|---|---|---|---|
| Engineering | 25,000 | 18,400 | 3,200 | 24,800 | −200 |
| Components | 40,000 | 12,000 | 22,500 | 38,000 | −2,000 |
| External laboratory | 15,000 | 2,100 | 8,900 | 16,800 | +1,800 |
| Installation | 20,000 | 0 | 0 | 20,000 | 0 |
| Project management | 12,000 | 6,800 | 1,200 | 13,200 | +1,200 |
| Contingency | 8,000 | 0 | 0 | 5,000 | −3,000 |
| Total | 120,000 | 39,300 | 35,800 | 117,800 | −2,200 |
If the review looks only at actuals, the project appears comfortable: €39,300 of €120,000 has been spent, about a third of the approved total. Once commitments are included, €75,100 is already spoken for. The forecast of €117,800 is still inside the approved budget, and part of the contingency is already assigned in that forecast. The line that needs a conversation is the external laboratory: the forecast is €16,800 against a budget of €15,000.
That is the value of the six columns together: the team can see the overall position and the line that requires a decision, in the same view.
What this template helps you catch
The same example shows three gaps that a simple list of amounts cannot surface on its own.
Commitments that sit beside the actuals. In the example, recorded spending is €39,300, and signed orders add another €35,800. A sheet without a commitments column would present a calmer picture than the one the review needs. With both columns filled in, the team can see the exposure that already exists and assign an owner to each open order.
A forecast that is an estimate, not a remainder. “Budget minus actuals” is arithmetic from the past. The forecast is the current view of where the line will land, with the assumptions written down. In the example the laboratory forecast moves above the approved line, while components stay below. The variance column makes that difference visible immediately.
Calculated totals that stay consistent. Variance and column totals work as formulas, so a change to actuals or commitments updates the picture for everyone who uses the file. The Microsoft documentation on Excel formulas is a reliable reference for operators and cell references. The practical rule is simple: if a number appears in two cells, a formula should connect them.
For a wider view of cost control during delivery, see the guide to project budget control.
How to set up the sheet
- A Parameters sheet: hourly rates, exchange rates and reserves live here and are referenced from the budget table, so the same figure is not rewritten in two places.
- A Budget sheet: one row per cost line, with the six columns above. Use a real Excel table (Insert > Table) so formulas extend to new rows.
- Calculated columns: variance as
=E2-B2(forecast minus budget), or=(C2+D2)-B2(actuals plus commitments minus budget) if a forecast has not been entered yet. Consumption on a line can be=C2/B2formatted as a percentage. A simple forecast is=C2+D2+G2, where column G is the estimate still required to finish the line. - One shared file: the working budget lives in a single current version. Protect the calculated columns and leave only the input cells editable, so the structure remains usable when more than one person updates it.
If you are starting from exported Project Online files, rebuild plan and budget from those records first with the guide After Project Online: rebuild your plan and budget from exported files, then place the cost lines into this template.
The ready-made file follows this structure: download the Excel project budget template.
From the Excel file to cost control in ControlRoom
When the six columns tell a clear story, the next step is to use that story in the project review, next to the plan and the open decisions. Bring the same line totals — budget, actuals, commitments and forecast — into a project in ControlRoom Free. You rebuild the essential cost picture from the figures you already trust, then keep it current for the next review.
The ten project review questions help turn the sheet into a short conversation: which line has the largest variance, which commitment has been open for weeks, and which forecast changed since the last plan update. The getting-started guide for ControlRoom Free walks through the first project from sign-up to that review.
A 76-second walkthrough on the product page shows that review in practice, with English narration and synthetic data. You can watch it below, or open it on the ControlRoom demo section.
Your next step
Start with the Excel project budget template and adapt it to your lines. For the review template and checklist, open the resources page; those files are available after leaving your email.
When the cost picture is clear, explore ControlRoom Free and use it in your next project review, with plan and budget in the same place.
Frequently asked questions
Which columns should a project budget template include?
Six: line, approved budget, actuals, commitments, forecast and variance. The first three describe what was approved and what has already been recorded. Commitments, forecast and variance show how much is already spoken for and where the line is likely to land.
How do I calculate the variance?
Use forecast minus budget for each line, or actuals plus commitments minus budget if you have not entered a forecast yet. Read the variance by line and in absolute value first: that is the prompt for the next review question.
Why keep commitments separate from actuals?
Because a purchase order or a signed contract can precede the invoice by weeks. If the sheet shows only actuals, the project looks less exposed than it already is. Recording commitments from the date of the order gives the review a complete cost picture.
What is the next step after the Excel template?
Download the Excel file and adapt it to your cost lines, then bring the same totals into ControlRoom Free so plan and costs sit together in the project review. The resources page also has a review template and checklist, and a short product demo shows that review in practice.
For evidence-based project control and a 10-minute review, explore how ControlRoom Free works, with templates and checklists to prepare your data.