This is lesson 5 of 10 in the project management basics course. In lesson 4 we built the time plan: durations, dependencies and the critical path. We now assign people to those same packages and check the workload. Only after that check can the durations be treated as feasible.
We stay with the illustrative example of the test-bench delivery: an approved budget of €120,000, a planned duration of six months shown as 26 calendar weeks, a client laboratory available only in the last three weeks, and some components with an eight-week lead time. These are sample figures and constraints, already written in the charter and in the schedule, not a real case.
Why the Gantt chart, on its own, is not enough yet
The schedule says how long a package lasts and what it depends on. It does not yet say who will do the work, or whether that person is free in the weeks where the package was placed. If two activities start in parallel and have the same person behind them, the durations from lesson 4 remain a hypothesis: on paper they fit 26 weeks; in a real week, they do not.
The benefit of this step is practical. Conflicts show up while you can still choose: move a piece of work, strengthen a role, or move a date with an explicit decision. You avoid discovering the overload on the eve of the factory test or the installation window.
Three questions, in this order:
- Who performs each package, with a recognisable name or role, not only a department?
- How many hours, or days, are needed in which weeks?
- Do those hours fit the person's real availability on this project?
Only after those answers is the critical path complete. A path that assumes resources are always ready is still a draft, as lesson 4 already noted.
Assignment, availability, load
The assignment links a package to the person who will take it to the finish. It often matches the owner already written in the WBS; sometimes the owner stays one person and the work is split between two. If roles overlap, the guide on how to create a responsibility matrix for a technical team is useful again.
Availability is the time that person can truly give to this delivery. In a mid-sized firm, designers and the workshop are rarely on a single project. A five-day week is not automatically a full week on the test bench.
The load is the comparison between the work assigned and that availability, week by week. If in one week the hours required exceed the hours available, there is an overload: it should be made visible and resolved, not left to the goodwill of someone who will «stretch a little».
This lesson stays with the plan for a single delivery. If the same people are shared across projects, the picture widens: the guide on allocating resources across multiple projects is already there. Here we close the test-bench plan first.
How to build it, step by step
- Start from the WBS packages and the windows in the schedule: who was the owner, and in which weeks the work falls.
- Go from the department to the person (or people) who will do the work. «Design» is an office; «mechanical designer» and «electrical designer» are assignments you can load.
- Estimate the hours for each package, with a basis: who estimated them, or on what. The hours must be consistent with the duration already declared: seven weeks of mechanical design at full time do not fit a designer who has three days a week on this delivery.
- Write down the real availability in the period, in hours or days per week.
- Place hours and availability on the same timeline and look for the weeks in which the sum exceeds capacity.
- Resolve conflicts explicitly, and reopen the schedule if the solution moves a date on the critical path.
The hours from this step will also be the basis for the labour budget, in lesson 6. It is better to close them here, while they can still be discussed, than to discover later a cost variance that started as a load that was never checked.
Example: the resources on the test-bench delivery
Illustrative example, not a real project. The team available for this delivery, typical of a mid-sized mechanical firm, is small: a part-time project manager, a mechanical designer, an electrical designer, two workshop technicians, plus purchasing time shared with other work. The hours below are a sample; the internal rate used to read them next to the budget, €50 an hour for engineering and project management, is equally illustrative, not a market benchmark.
The approved engineering line is €25,000. At the sample rate that is 500 hours. A split consistent with the WBS packages and with the windows in lesson 4 can look like this.
| Package | Who does the work | Window | Sample hours | Implied load |
|---|---|---|---|---|
| Mechanical design | Mechanical designer | Weeks 1-7 | 180 | About 26 hours a week |
| Electrical design and cabinet | Electrical designer | Weeks 2-7 | 150 | 25 hours a week |
| Test sequence and protocol | Electrical designer (owner) and mechanical support | Weeks 3-7 | 80 (50 + 30) | About 10 + 6 hours a week |
| Specification freeze | Both designers, with the project manager | Week 8 | 16 | Two shared days |
| Support to the factory test | Both designers | Weeks 21-22 | 40 | 20 hours a week, between two people |
| As-built documentation | Mechanical designer | Weeks 21-23 | 24 | 8 hours a week |
| Training of two technicians | Mechanical designer | Week 25 | 10 | A day and a half |
| Engineering total | 500 | Aligned with the €25,000 line |
The project manager, on the €12,000 line, has 240 sample hours: about 9 hours a week over 26 weeks, with peaks in week 8 (the freeze) and week 26 (acceptance). The two workshop technicians cover the build, the factory test, transport and installation in weeks 17-25; purchasing follows the long-lead orders from weeks 8 to 16, without a dedicated budget line.
The point this table makes visible sits in weeks 3-7. If the entire test sequence were assigned to the mechanical designer, already committed for 26 hours a week on mechanical design, the load would rise by another 16 hours: over 40 hours a week on the test bench alone. In that hypothesis, the durations from lesson 4 would not stand up.
The resolution, in this example, is explicit: the test sequence is owned by the electrical designer (50 hours), with limited support from the mechanical designer (30 hours). In weeks 3-7 the mechanical designer then stays around 32 hours a week and the electrical designer around 35. It is a high load, but it is a declared load, not double work hidden behind the same duration.
Two other overlaps are worth checking at once, even though in this example they hold:
- In weeks 21-23 the mechanical designer supports the factory test and closes the as-built documentation: 10 hours of support plus 8 of documentation, about 18 hours a week. If the as-built work were squeezed only into the two test weeks, that margin would disappear.
- In week 25 the two technicians are on site for installation and the mechanical designer runs the training. Installation stays on the critical path: training, already fitted into that week, cannot slip without putting acceptance in week 26 at risk.
The benefit of seeing this now is that you can confirm the durations, or reopen the schedule, before you commit suppliers and the laboratory window. In lesson 6 these same hours become the labour lines of the budget.
Mini-exercise and checklist
Take the packages from your own WBS, or from the test-bench one, and build a table with the person who does the work, the window, the hours and the weekly availability. Mark at least one week in which two packages touch the same person. Then check:
- ☐ Every WBS package has a recognisable person doing the work, not only a department.
- ☐ The hours have a basis (who estimated them, or on what) and are consistent with the duration already declared.
- ☐ Availability is the real time on this delivery, not a full week taken for granted.
- ☐ Parallel activities in the schedule have been checked on the same people, not only on the bars.
- ☐ At least one load conflict is visible, with an explicit response (another person, less content, or a replanned date).
- ☐ If the solution moves an activity on the critical path, the effect on the finish is stated.
- ☐ Peaks near the factory test, installation and acceptance have been looked at with care.
- ☐ The labour hours are ready to enter the budget, without postponing the arithmetic until later.
If a duration «fits» the Gantt chart and does not fit the load, the load wins: you replan now, not in the workshop.
Previous and next lesson
Lesson 4 set the durations, dependencies and the critical path. Lesson 6, planned for 26 November, moves on to the project budget: estimates, baseline and commitments, on the same lines already named in the charter and in the project budget template. The course index is on the hub page.