This is lesson 4 of 10 in the project management basics course. In lesson 3 we broke the scope into work packages. We now build the time plan on those packages: durations, dependencies and the critical path. The Gantt chart is how you see that logic, not a substitute for the logic.
We stay with the illustrative example of the test-bench delivery: an approved budget of €120,000, a planned duration of six months, a client laboratory available only in the last three weeks, and some components with an eight-week lead time. These are sample figures and constraints, already written in the charter, not a real case.
Durations and links first, bars afterwards
A schedule answers three questions, in this order:
- How long does each piece of work take?
- What must finish, or start, before something else can proceed?
- Which external constraints do not depend on us, but still move the dates?
Only after those answers does it make sense to draw the bars. The Gantt chart makes the whole picture visible: when an activity starts, how long it runs, how it fits with the others. If the bars are born from dates chosen by eye, the drawing holds until the first slip and then stops explaining why the end date moved.
Durations are estimates, not hopes. They are made by the people who will do the work, or at least recognised by them. A duration with no basis («seven weeks of mechanical design, estimated by the design office on a similar delivery») is a fragile number. In this lesson we do not yet load the people: a plan that ignores workload will be completed in lesson 5. What we want here is a time logic that can be discussed.
Dependencies and constraints, kept simple
The most useful relationship, at the start, is finish-to-start: activity B starts when activity A has finished. That is enough to describe most of the test-bench work: you do not freeze the specification before the designs are released, you do not order long-lead material before the freeze, you do not run the factory test before the bench has been built.
Alongside the dependencies sit the external constraints. They are not a quirk of the calendar. In the example, two are already known:
- the long-lead components arrive eight weeks after the order;
- the client laboratory is available only in the last three weeks.
These constraints are declared, not «made to fit» by sliding the bars. Other relationships, such as start-to-start, are used only if there is a real link (for example electrical design that can start once mechanical design is under way, not necessarily finished). They are not there to compress the drawing.
The critical path
The critical path is the longest chain of linked activities between the start and the finish. It sets the earliest date on which the project can close. If an activity on that chain slips by a week, the finish slips by a week, unless you change something explicit: a duration downstream, a dependency, or a constraint.
Activities that do not sit on that path have a margin (the float): they can slip a little without moving the finish date. That margin is a management resource, not an invitation to start late out of habit. It should be seen, not discovered on the day it has already been used up.
Drawing the Gantt chart without having found the critical path leaves the conversation about «we are late» with no point of attack. With the path visible, the question becomes concrete: is an activity slipping that moves the finish, or is it consuming a margin that was there?
If you want to go from the logic to a drawing in a spreadsheet, the guide Gantt in Excel vs Gantt online: what really changes is already there. It shows how to build a Gantt chart in Excel and where that tool struggles, in particular with dependencies, baselines and team updates. This lesson does not repeat those steps: it stays with the logic of the plan, which has to be in place before the tool.
Example: the schedule for the test-bench delivery
Illustrative example, not a real project. The planned six months are represented here as 26 calendar weeks, so that durations and slips are easy to see. The weeks are a sample; they are not the calendar of a real delivery.
We start from the packages in lesson 3 and from two assumptions already in the charter: the long-lead components are ordered right after the specification freeze, and installation happens only in weeks 24-26.
| Activity | Duration | Depends on | Sample window | Notes |
|---|---|---|---|---|
| Mechanical design | 7 weeks | Start | Weeks 1-7 | Design-office estimate, example |
| Electrical design and cabinet | 6 weeks | Start of mechanical design | Weeks 2-7 | Can run in parallel, with a one-week offset |
| Test sequence and protocol | 5 weeks | Start | Weeks 3-7 | Must be agreed before the freeze |
| Specification freeze | 1 week | The three design releases | Week 8 | Clean starting point for the orders |
| Order and arrival of long-lead components | 8 weeks | Freeze | Weeks 9-16 | A supplier constraint, not a workshop one |
| Fabrication and remaining materials | 5 weeks | Freeze | Weeks 9-13 | Has margin relative to the long lead time |
| Workshop build | 4 weeks | Arrival of the long-lead components | Weeks 17-20 | Does not start before the motors and sensors |
| Factory test | 2 weeks | Build | Weeks 21-22 | Includes internal rework |
| Transport and site preparation | 1 week | Factory test | Week 23 | Often forgotten in the WBS |
| Installation and commissioning | 2 weeks | Transport; laboratory window | Weeks 24-25 | Only in the last three weeks |
| Training of two technicians | 1 week | Commissioning under way | Week 25 | Can overlap the end of installation |
| As-built documentation | 3 weeks | Factory test | Weeks 21-23 | Has margin: it only needs to be ready at acceptance |
| Acceptance | 1 week | Installation, training, as-built | Week 26 | Closes the success criteria in the charter |
The critical path in this example is visible at a glance:
mechanical design → specification freeze → eight-week lead time → build → factory test → transport → installation → acceptance.
That is 7 + 1 + 8 + 4 + 2 + 1 + 2 + 1 = 26 weeks. The delivery reaches acceptance at the end of the sixth month, with no margin on the path. Electrical design, fabrication and the as-built documentation are not on that chain: they have float. Training, fitted into week 25, is in practice on the path to the finish: if it arrives late, acceptance in week 26 is at risk.
Two consequences already useful in a review, before you even open a chart:
- If the freeze slips by two weeks, the components arrive in weeks 11-18, the build occupies weeks 19-22, the factory test weeks 23-24, transport week 25. Installation loses the three-week window, or is squeezed against acceptance. This is not a delay to «make up in the workshop»: it is a mechanical effect of the path.
- A laboratory that is only available at the end is not an excuse to start slowly. It is a constraint that already sits at the end of the path. The margin is not there: if anywhere, it is on fabrication or on the as-built documentation.
The Gantt chart of this schedule is the view of the same rows on a timeline. When you update a duration or a dependency, you update the logic first and the drawing afterwards. The guide to the Gantt in Excel helps you build that view; it does not replace the dependency table.
In lesson 5 we will check whether these durations remain feasible with the people available. A critical path that assumes resources are always ready is still a draft.
Mini-exercise and checklist
Take eight to ten activities from the WBS of your own project, or from the test-bench one, and build a table with duration, predecessor and, if there is one, an external constraint. Mark the longest chain and the finish date. Then move the earliest activity on that chain by two weeks and watch what happens to the delivery. Check:
- ☐ Every activity has an estimated duration and a basis (who estimated it, or on what).
- ☐ Dependencies are written down, mostly finish-to-start, and describe a real link.
- ☐ External constraints (lead times, client windows) are visible, not absorbed by sliding the bars.
- ☐ The critical path is identified and leads to an explicit finish date.
- ☐ At least one activity off the path has a margin that is understood, not only a vague «we will do it earlier».
- ☐ A slip on the path has a stated effect on the finish, not a vague recovery.
- ☐ The Gantt chart, if there is one, is a view of this logic, not a set of dates chosen by eye.
- ☐ We have not yet taken the people's workload for granted: that check is the next step.
If the finish date does not fit the six months, or fits with no margin on the path, the conversation to have now is with the sponsor, not on the eve of the installation window.