Risks and issues: register, owners, responses

A time and cost plan becomes manageable when what can still move it is visible: risks, issues, an owner and a response. In this lesson we build a simple register for the example test-bench delivery.

This is lesson 8 of 10 in the project management basics course. In lesson 7 we compared budget and actuals, with commitments and forecast. Next to those numbers we now put what can still move them: risks and issues.

We stay with the illustrative example of the test-bench delivery: a mid-sized mechanical company in Northern Italy delivers a custom test bench into a client laboratory. Approved budget: €120,000. Planned duration: six months. We are at mid-project, around week 14 already used in lesson 7, with the same constraints already written in the charter: components with an eight-week lead time, and a client laboratory available only in the last three weeks. These are sample figures and constraints, not a real case.

Why the plan and the costs are not enough yet

An updated Gantt chart and a forecast that still sits inside the budget can make the delivery look calm. The missing question is: what can still move that date or that total, and who is looking after it? Without an explicit answer, the signals arrive late: a supplier that slips, a client window that shortens, a «while you are at it» request that widens the work.

A short register makes these items visible before the review. It is not a list of fears and not a diary of tasks. It is the list of what can change the plan, or is already changing it, with an owner and a response. In lesson 9 these lines feed the status you take to steering; in lesson 10 a request that falls outside the scope becomes a change, not a line added in silence.

Risk and issue, in operational language

A risk is an event that might happen. It has a likelihood and an effect on dates, costs or quality. You can reduce it, avoid it, transfer it or accept it, but it has to be stated. An issue is a problem already in progress: likelihood has become a fact. You close it with an action, a decision or a new baseline, not with a «let's see if it happens».

Keeping them on the same sheet helps you not to lose them. Distinguishing them stops you from treating a fact as a hypothesis, or from leaving a risk without an owner because «it is not a problem yet». When a risk materialises, the line changes type and the response becomes a closure, not an estimate.

Three practical rules:

  • One line, one owner, one next action. An item without an owner ages in silence.
  • The effect is concrete. «A possible delay» is not enough: you say whether it moves the critical path, a budget line or an acceptance criterion.
  • A few items, the ones that matter. A register of fifty lines stops being read. In a review you bring the items that need a decision, not the whole list.

At the start a simple scale (high, medium, low) on likelihood and impact is enough. You do not need a sophisticated map to begin: you need the register to be up to date and recognised by the people doing the work.

How to keep the register, step by step

  1. Start from the plan and the forecast already in use, and ask what can move them: suppliers, client windows, key people, scope requests, tests and acceptance.
  2. Separate what might happen (a risk) from what is already happening (an issue).
  3. For each item, write the effect on a date or a budget line, in one sentence.
  4. Assign an owner who updates the line and a response under way, with a deadline or a trigger («if the supplier slips by more than a week, we take the decision to the review»).
  5. Close or downgrade items that no longer have an effect. A register that is never cleaned loses sight of what is still open.
  6. Take to the review only the items that need a decision, each with an owner and an alternative.

The responses, in operational form, are few. You can reduce likelihood or impact (an earlier order, a check halfway through the lead time, a frozen protocol). You can avoid the cause, if a real alternative exists. You can transfer part of the risk to a supplier, within an agreement already written. You can accept the risk, but with a visible margin: a share of contingency, a declared float, a review date. Accepting without a margin is leaving the risk unnamed.

Example: the register for the test-bench delivery

Illustrative example, not a real project and not a measured ControlRoom result. We are at a mid-project review, around week 14, consistent with the figures already used in lesson 7, in the project budget template and in the guide to the steering report in PPTX. The sample overall forecast remains at €117,800 against an approved €120,000. The external laboratory line has a forecast of €16,800 against a budget of €15,000, because the protocol requires more tests than the original quote.

IDTypeDescriptionEffect (example)OwnerResponseStatus
R1RiskLong-lead components arrive after week 16Moves build and in-house test, and compresses the installation window in weeks 24-26, already on the critical pathProject manager, with procurementConfirm supplier dates halfway through the lead time; if the slip exceeds one week, take the decision to the reviewOpen
R2RiskThe client laboratory is not available in the last three weeksAcceptance no longer falls at the end of month six, because installation has no margin on that windowProject manager, with the client counterpartConfirm the slot in writing before the shop-floor buildOpen
R3RiskThe test protocol widens after an informal requestPushes the external laboratory line up further and can move the in-house testProject manager, with engineeringIt is not widened in silence: it becomes a change requestOpen
I1IssueThe external laboratory forecast is at €16,800 against a budget of €15,000A variance of €1,800 on that line; part of the contingency is already implied in the forecastProject manager, with engineeringAsk the review to allocate €1,800 of contingency formally and to freeze the protocolOpen, to take to the review

What you can already see from this table, before any slide:

  • Risks R1 and R2 sit on the path that in lesson 4 had no margin. They are not a «delay to recover in the workshop»: they are mechanical effects on the finish date.
  • Issue I1 is already a fact, not a hypothesis. It is the item that, in the review, asks for a decision on contingency and on the protocol.
  • Risk R3 protects that very decision: if the protocol widens after the allocation, the variance starts growing again in silence. The right response is a change, not an informal adjustment of the WBS.

Two or three items, each with an owner and a response, are enough for this example delivery. The register does not replace the plan: it explains what can still move it.

Mini-exercise and checklist

Take your own project, or the test-bench delivery, and build a one-page register: at most eight items, risks and issues, with type, effect, owner, response and status. Then check:

  • ☐ Risks and issues are distinct: what might happen is not mixed, unlabelled, with what is already under way.
  • ☐ Every item has a concrete effect on a date, a budget line or an acceptance criterion.
  • ☐ Every item has a recognisable owner and a next action, with a deadline or a trigger.
  • ☐ Items that sit on the critical path, or on a line already in variance, are explicit.
  • ☐ Acceptance of a risk has a declared margin; it is not a «we will see».
  • ☐ A request that falls outside the scope is marked as a change, not added to the work in silence.
  • ☐ The register is short enough to reread before a review.
  • ☐ The people doing the work recognise the items, or the points still open are visible.

If an item has no owner or no declared effect, it is not yet ready for steering: it needs to be clarified now.

Previous and next lesson

Lesson 7 kept budget, actuals, commitments and forecast together. Lesson 9, planned for 1 December, moves on to status and the review: the status report, steering and the cockpit, starting from these items. The course index is on the hub page.