Project budget: estimate, baseline and commitments

With packages and hours in hand you can build the budget: estimates aligned with the WBS, an approved baseline and room for commitments. In this lesson we apply that to the example test-bench delivery.

This is lesson 6 of 10 in the project management basics course. In lesson 5 we assigned people and checked the loads. Those hours, together with materials and services, now become a project budget: estimates aligned with the WBS, an approved baseline, and room for commitments.

We stay with the illustrative example of the test-bench delivery: an approved budget of €120,000, a planned duration of six months, and the same lines already named in the charter (engineering, components, external laboratory, installation, project management, contingency). These are sample figures, not a real case, and they match those in the guide to the Excel project budget template.

From WBS estimates to an approved reference

A useful budget is born from the work packages, not from a total decided on the side and then spread across the lines. Each line has a basis: hours already discussed in lesson 5, materials from the purchasing packages, external services required by the protocol. When the estimates are visible, the sponsor can approve a reference the team recognises.

That reference, once approved, is the baseline. It is the version against which, from this point on, variances will be read. If the total moves in silence at every update, the review loses its point of attack: it is no longer clear what had been agreed.

Three steps, in this order:

  1. Estimate each line from the packages, with a stated basis.
  2. Have the sponsor recognise the picture and freeze it as the baseline.
  3. Prepare, already in this sheet, the columns that delivery will need: actuals, commitments, forecast and variance.

The third step does not mean that actuals already exist. It means the budget is born ready to be governed, not as a list of amounts that will have to be rewritten later.

The six columns, and the role of commitments

The minimum structure is the same as in the guide to the budget template, which remains the practical page on the Excel file. What matters here is the meaning, on the test-bench delivery:

ColumnWhat it holds on this delivery
LineThe cost item, aligned with the packages: engineering, components, external laboratory, installation, project management, contingency
BudgetThe approved value of the line, the baseline
ActualsCosts already incurred and recorded: hours booked, invoices received
CommitmentsOrders and contracts already issued, not yet recorded as actuals
ForecastThe current estimate of where the line will land
VarianceForecast minus budget

The first two columns are closed in this lesson. The others are filled in during delivery: that is the subject of lesson 7. It is still worth having a commitments column already, because the first important order on this delivery goes out right after the specification freeze, in week 9. Without that column, the budget would tell only what has already been invoiced, and the long-lead components would stay invisible for weeks. The guide to commitments versus actual costs explains why the two views belong side by side.

Example: the approved budget for the test-bench delivery

Illustrative example, not a real project. At the start, after the estimates and before any order, the baseline of the delivery is the table below. The totals match the example already published in the budget template guide.

LineApproved budgetBasis of the estimate, in this example
Engineering25,000500 internal hours at the illustrative rate of €50 an hour, split as in lesson 5
Components40,000Motors, sensors and fabrication materials from packages 3.1 and 3.2
External laboratory15,000Calibration and specialised tests placed with a third-party laboratory, distinct from the in-house factory test, and required by the protocol
Installation20,000Rolls up the workshop build, the factory test, transport and installation at the client: labour of the two technicians and site costs
Project management12,000240 internal hours at the same illustrative rate of €50 an hour, across the 26 weeks
Contingency8,000The delivery reserve, to be used only with an explicit decision
Total120,000The approved budget in the charter

Two readings are already useful, before any actuals appear.

First: the lines speak the same language as the WBS. Engineering covers mechanical design, electrical design, the test sequence, the freeze, support to the factory test, the as-built documentation and training. Components cover purchasing. The external laboratory is a supplier service, not workshop hours. Installation, under the name already used in the charter and in the template, gathers the work that comes after design and materials: to govern it more closely you can keep internal sub-lines (build, factory test, transport, commissioning) that still add up to €20,000.

Second: contingency is visible and still untouched. It is not a margin to be absorbed in silence inside the other lines, and it has not already been spent. In lesson 7 we will see a moment, halfway through the delivery, when part of this reserve is assigned in the forecast: that is a decision, not an automatic adjustment.

At the start, actuals and commitments are zero. The first typical movement, in this example, comes in weeks 8-9: after the freeze, the long-lead components are ordered. From that day, part of the €40,000 is already committed, even if the invoice will arrive later. The sheet is ready to record it.

The hours from lesson 5 and these amounts belong together: if the mechanical designer's load went back to 40 hours a week, the €25,000 engineering line would not be enough, or the durations would have to be replanned. Closing the loads first avoids a budget that only «adds up» on paper.

Mini-exercise and checklist

Take the packages from your own WBS, or from the test-bench one, and build a one-page budget: a few lines, each with a basis for the estimate, and a total for the sponsor to recognise. Then check:

  • ☐ Every line has a basis (hours, materials, a service) linked to one or more WBS packages.
  • ☐ Labour hours match the load already checked, not a total decided on the side.
  • ☐ The total matches the approved budget in the charter, or a gap has already been taken to the sponsor.
  • ☐ There is a recognised baseline, line by line, that will remain the reference for the reviews.
  • ☐ Contingency is a visible line, with a rule for using it, not a hidden margin.
  • ☐ The sheet already has columns for actuals, commitments, forecast and variance, even if they are empty at the start.
  • ☐ Long-lead purchases have a line (or a sub-line) ready to record the first commitment.
  • ☐ The Excel template, if you use it, is adapted to these lines, not a copy detached from the plan.

If a line cannot be explained with a package, it is not yet ready for approval: it should be broken down or clarified now.

Previous and next lesson

Lesson 5 assigned the people and checked the loads. Lesson 7, published on 29 November, moves on to cost control during delivery: budget vs actuals, commitments and forecast, on the same delivery at mid-point. The course index is on the hub page.