Budget vs actuals: commitments and forecast

With an approved baseline you can steer cost during delivery: actuals, commitments and forecast on the same row. In this lesson we apply that to the example test-bench delivery, at mid-point.

This is lesson 7 of 10 in the project management basics course. In lesson 6 we closed the baseline: €120,000 approved, line by line. That reference now serves to steer cost during delivery. You compare budget and actuals, give commitments a place, and keep the forecast current.

We stay with the illustrative example of the test-bench delivery. The figures in this lesson are the same ones already published, as a mid-project review example, in the guide to the Excel project budget template. They are not a real case and not a ControlRoom result.

Not only what has already been invoiced

Halfway through a delivery, the typical risk is to read only the actuals: how much has already gone out, against the approved total. If that is the only column, the conversation stays in the past. The benefit of putting commitments and the forecast on the same row is a different one: you see how much is already spoken for, and where the line is likely to land, in time for a decision.

Three readings, always together:

  1. Actuals: costs already incurred and recorded.
  2. Commitments: orders and contracts issued, not yet recorded as actuals. The guide to commitments versus actual costs explains why the two views belong side by side.
  3. Forecast: the current estimate of the final cost of the line, with the assumptions written down. It is not «budget minus actuals»: that is arithmetic on the past, not a forecast.

The most useful variance in a review is forecast minus budget. Look first at the line with the largest variance in absolute value: that is the one that deserves a question, even when the total is still inside the baseline. The guide to real-time project budget control takes a related point further: arriving at the review with the figures already aligned, not with actuals that describe a spend already closed.

What to ask of each line

For each line, in a review, a few questions are enough:

  • How much has already been spent, and how much is already committed?
  • Is the forecast still the baseline, or has it changed, and on what assumption?
  • If there is a variance, who owns it and which decision is needed (use contingency, replan, or take an adjustment to the sponsor)?

Contingency, closed as a line in lesson 6, comes into play here. You do not «draw» from that reserve in silence: you assign part of it in the forecast, with a visible decision. The ten questions of a project review that decides help keep that conversation short and conclusive. Once the figures are stable, the same picture can go into a steering report in PPTX.

Example: the mid-point review of the test-bench delivery

Illustrative example, not a real project. We are around week 14: the specification freeze is closed, the long-lead component order is under way (arrival planned for week 16), and the workshop build has not started yet. It is the right moment for a cost review, because the commitments are already there and the decisions still arrive before the factory test and the installation window.

LineBudgetActualsCommitmentsForecastVariance
Engineering25,00018,4003,20024,800−200
Components40,00012,00022,50038,000−2,000
External laboratory15,0002,1008,90016,800+1,800
Installation20,0000020,0000
Project management12,0006,8001,20013,200+1,200
Contingency8,000005,000−3,000
Total120,00039,30035,800117,800−2,200

If the review looked only at actuals, the delivery would seem comfortable: €39,300 of €120,000 has been recorded, about a third of the approved total, at mid-calendar. Once commitments are added, €75,100 is already spoken for. The forecast of €117,800 stays inside the baseline, and part of the contingency is already assigned in that forecast.

The line that deserves a conversation is the external laboratory: a forecast of €16,800 against a budget of €15,000. In this example the order went out after the freeze, together with the agreed protocol; some preliminary work has already been invoiced (€2,100), the open commitment is €8,900, and the forecast has risen because the protocol requires additional tests beyond the original quote. This is not a cost that «appeared in the workshop»: it is a variance visible in week 14, when a decision can still be made.

Beside it, project management has a forecast of €13,200: the hours already booked, plus the extra coordination on the protocol and the orders, take the line €1,200 above the baseline. Engineering and components, by contrast, stay under: most of the design work is behind us, and purchasing closes with a forecast of €38,000. Installation is still untouched, as the schedule intended, and its forecast remains €20,000.

Contingency absorbs, in the forecast, the €1,800 on the laboratory and the €1,200 on project management: €3,000 assigned, €5,000 still free. The total remains €2,200 under the baseline. The decision to take now, and to write down, is precisely this: do we use part of the reserve for the additional tests and the coordination, or do we revisit the content of the protocol? The fact that the total still holds is the margin with which you can choose calmly, not a reason not to choose.

This is the same picture already used in the template guide: the course and the template stay aligned, with different roles. The template shows how to keep the sheet; this lesson shows how to read it in a review, on the course delivery, in week 14.

Mini-exercise and checklist

Take the budget of your own delivery, or this table, and run a one-page review: actuals, commitments, forecast and variance, plus a proposed decision on the most exposed line. Then check:

  • ☐ Every line has actuals and commitments updated to the date of the review, not only a spend total.
  • ☐ The forecast is an estimate with a written assumption, not an arithmetic remainder (budget minus actuals).
  • ☐ Variance is calculated as forecast minus budget, and you look first at the line with the largest variance.
  • ☐ The sum of actuals and commitments (the exposure already in place) is visible on the total.
  • ☐ If a line is above the baseline, there is a proposed decision: contingency, a replan, or an adjustment.
  • ☐ The use of contingency, if any, is assigned in the forecast and not absorbed in silence.
  • ☐ Lines still at zero (here, installation) still have a forecast, not a blank.
  • ☐ The same picture can go into the review with the sponsor, and later into a steering report.

If the total is inside the baseline and a line is not, the useful conversation is on the line: that is where you decide, while the margin is still there.

Previous and next lesson

Lesson 6 set the estimates, the baseline and the structure for commitments. Lesson 8, published on 30 November, moves on to risks and issues: a register, owners and responses, including those that start from the variances this review has made visible. The course index is on the hub page.